Renovation Payment Schedule Malaysia: Deposit & Progress Payments

Published

A typical renovation payment schedule in Malaysia starts with a 10–20% deposit on confirmation, followed by progress payments tied to finished stages of work, a payment at handover and a retention of about 5% released after the defects period. Homeowner guides treat a deposit above 30% as a warning sign, and CIDB advises that payments follow the percentage of work completed. Write the schedule, the payment terms in days and the retention into the quotation, so there is nothing to argue about later.

How much renovation deposit is normal in Malaysia

The deposit secures the client’s slot and covers your early costs. Published guides give a fairly consistent range:

Source Deposit guidance
Qanvast (2024) 10–20%, sometimes up to 30%, usually non-refundable; warns about requests of up to 50%
PropertyGuru 15–20% of the total cost, generally non-refundable
Recommend.my (2024) No more than 30% for bigger projects; never full payment upfront

The trust problem is real. In 2024 CIDB’s chief executive said contractors often disappear after receiving the advance payment, and that verbal agreements are not enough. A client who has read that will be wary of a large deposit, so a modest deposit with clear milestones often wins the job faster than a big one.

CIDB’s own standard renovation contract treats the advance as an amount the parties write in, with a default of nil if it’s left blank. If you need more upfront for long-lead items, such as custom carpentry or imported tiles, say what the money buys and put it on its own line.

Progress payments tied to milestones

After the deposit, tie each payment to a stage the client can see on site. CIDB’s advice to homeowners is that payments should follow the percentage of work completed, and PropertyGuru recommends paying in stages linked to specific milestones. Good milestones are:

  • Hacking, masonry and wet works completed (tiling, screeding, waterproofing).
  • Electrical and plumbing first fix completed, before the ceiling closes.
  • Carpentry installed, or delivered to site if you agree that in writing.
  • Practical completion and handover, with a short defects list.

Avoid dates (“payment on 15 March”) as milestones. If work slips, you’ll be chasing a payment for work that isn’t done, and the client will refuse. Avoid vague stages too (“50% progress”), because nobody can agree what 50% looks like.

Long jobs can use monthly valuations instead: you claim the value of the work done each month. CIDB’s standard contract works this way unless the parties attach a stage payment schedule.

Sample renovation payment schedule (illustrative)

This is an illustrative schedule for an RM80,000 condo renovation. Adjust the stages to the trades in your job.

Stage Milestone % Amount (RM)
1 Deposit on signed quotation 15% 12,000.00
2 Hacking, masonry and wet works completed 30% 24,000.00
3 Carpentry, electrical and plumbing installed 30% 24,000.00
4 Practical completion and handover 20% 16,000.00
5 Retention, released after the defects period 5% 4,000.00
Total 100% 80,000.00

Check that the percentages add up to 100% and that the amounts add up to the contract sum. When the client approves a variation order, state on the VO which payment it’s added to, so the schedule and the revised contract sum still match.

Payment terms: how many days to pay

A milestone tells the client when a payment falls due. You also need to say how quickly they must pay. Write it in days, for example “payable within 7 days of our invoice”.

  • CIDB’s Standard Terms of Construction Contract for Renovation and Small Projects lets the parties fill in the period. If it’s left blank, the client must pay within 7 days of each payment certificate.
  • The same contract lets the contractor give written notice for an unpaid certificate and suspend work if the client still hasn’t paid 7 days after receiving that notice.
  • Where the Construction Industry Payment and Adjudication Act 2012 (CIPAA) applies and the contract has no payment terms, the default is monthly progress payments, due 30 calendar days from receipt of the invoice.

Mah Weng Kwai & Associates advises homeowners to pay promptly when payments are due, and notes that non-payment may lead a contractor to slow down or stop work. Clear terms protect both sides.

Retention: hold back a small final sum

Retention is a part of the price the client keeps until defects are fixed. Published figures vary:

Source Retention
CIDB, via NST (2024) 5–10% of the contract value, paid after the work is complete and the owner is satisfied
CIDB standard renovation contract 10% of each certified amount, capped by default at 5% of the total price
Mah Weng Kwai & Associates (2020) Usually 10%, sometimes more on small contracts

Under the CIDB contract’s defaults, the defects liability period is 12 weeks from practical completion, and the retention is released with the final account within 30 days of the final completion certificate. The contract also lets the contractor provide performance guarantee insurance instead of retention. If you’d rather not have retention deducted from every claim, the simpler option for small jobs is a single 5% stage at the end, as in the sample above.

Does CIPAA apply to renovation work?

CIPAA gives contractors a fast adjudication route for unpaid claims. It covers construction contracts made in writing, and its definition of construction work includes renovation and alteration. Under CIPAA a contractor serves a written payment claim, and the client has 10 working days to respond. Clauses that make payment depend on the payer first being paid by someone else, or on its financing being available (“pay when paid”), are void.

There’s an important exclusion in section 3. CIPAA does not apply to a contract entered into by an individual for work on a building under four storeys that is wholly intended for that person’s own occupation. Many owner-occupied landed houses fall into that exclusion. In Liew Piang Voon v WLT Project Management (2020), as summarised by Donovan & Ho, the High Court held that the exclusion did not apply where the owner renovated a house for his daughter to run a kindergarten, because he would not occupy it himself.

Company clients, shops, offices and work on buildings of four storeys or more are more likely to be inside CIPAA. Whether a particular job is covered depends on the facts, so check with a lawyer before relying on it.

This section is general information, not legal advice.

What to write in the quotation

  • The schedule itself: stage, milestone, percentage and RM amount, adding up to 100%.
  • Payment terms in days from your invoice, and how to pay (bank transfer to your company account).
  • Retention: percentage, and when it’s released.
  • Variations: priced in writing before the work, and which payment they’re added to.
  • What happens if a payment is late: for example, that you may suspend work after written notice.
  • Validity: how long the price and schedule hold.

CIDB has offered free sample contracts for renovation and small projects since 2015. Using one, or attaching your quotation to one, gives the client terms they can check against a recognised standard.

Put the schedule in every quotation

Our free renovation quotation template already has a five-stage payment schedule that warns you if it doesn’t add up to 100%. Interior designers can see how the design fee fits into the schedule in the interior design quotation guide, and the markup vs margin guide shows what each payment actually leaves you after costs. In QCON, every line keeps your cost and selling price, so you know your margin before you agree the deposit.

Sources

Frequently asked questions

How much deposit should I ask for a renovation in Malaysia?
Malaysian homeowner guides describe 10–20% of the contract sum as the usual deposit, sometimes up to 30%. Qanvast warns homeowners about contractors asking for as much as 50% upfront, so a deposit above about 30% makes clients nervous.
What is a normal renovation payment schedule?
A deposit on confirmation, then progress payments when visible stages are finished, such as wet works, carpentry and electrical, then a payment at handover and a small retention released after the defects period. CIDB advises that payments follow the percentage of work completed.
How long does a client have to pay a renovation progress payment?
Whatever your contract says. CIDB's standard renovation contract uses 7 days from the payment certificate if the parties don't fill in a different period. Where CIPAA applies and the contract is silent, the default is 30 calendar days from receipt of the invoice.
Does CIPAA apply to home renovation?
CIPAA 2012 covers written construction contracts, including renovation, but it does not apply to a contract made by an individual for a building under four storeys that is wholly for that person's own occupation. Many owner-occupied landed houses fall in that exclusion, so check with a lawyer for your job.
How much retention is held in a renovation contract?
CIDB has suggested 5–10% of the contract value. Its standard renovation contract deducts 10% from each payment, capped by default at 5% of the total price, and releases it after the defects liability period.